The City of Spring Lake Park is planning the 2026 Street Improvement Project as part of its ongoing pavement management program. The proposed project is intended to preserve existing streets, extend pavement life, and maintain safe, functional roadways for residents, businesses, and visitors. The feasibility report identifies the project as a mill and overlay project with select curb and gutter repairs, consistent with recent street improvement work completed in the city.
The proposed 2026 Street Improvement Project includes improvements to:
The project consists primarily of a 2-inch mill and overlay, along with select repairs to existing concrete curb and gutter, replacement of certain castings, and related restoration work. The project does not include major utility reconstruction. No sanitary sewer or water main upgrades are proposed as part of this work.
These streets were largely last paved in 1997, with the TH 10 Service Drive last paved in 2001. The report concludes that the proposed improvements are necessary and cost-effective based on the age and condition of the existing streets and the City’s long-standing street maintenance practices.
The total estimated project cost is $577,200. Of that amount, approximately $501,592 is proposed to be assessed to benefiting properties, with the remaining share funded by the City in accordance with established assessment practices.
The proposed assessment rates in the feasibility report are:
The feasibility report outlines the following proposed timeline for the project: